I want to finish some more outside work before the cold weather starts in earnest so I've started finishing the interior of the utility room. I wired up the AC electrical panel, added insulation, and started sheathing the inside walls with OSB. I framed in a ceiling with access to the "attic". The "attic" is a very small space but provides a place to run wiring and piping more easily and neatly.

I also worked on a few other miscellaneous tasks. I installed the bathroom door, installed light fixtures in the living room and kitchen, and wired up some of the wall switches and sockets.