This past weekend I installed sheathing on the utility building. I had enough of the Zip Systems sheathing left over for all but one side of the building. I used standard OSB for that side, covered in 30lb tar paper.
I also installed purlins on the roof of the utility building and cleaned up around the cabin. There was a large bird flying around in the loft that I couldn’t get out. Hopefully it will fly out before this weekend. I really need to close in the one remaining open eave.
I’m having the siding delivered this week so if all goes well, I’ll start siding this weekend.